Upcoming EventsLocationFacility InformationSeating ChartsNewsContact UsMTS IceplexWinnipeg Jets
Thursday, May 6, 2004

Construction Briefing


The structural slab for the future ice floor at MTS Centre is now about 50% complete. Forming and pouring the remainder of the ice floor will take place over the next week. The ice floor dimension will accomodate both the North American professional (85' x 200') or the larger (100' x 200')international ice surface.


Another perspective of the interior of the future seating bowl at MTS Centre looking east with daylight still streaming in at the private suite level where the final suite walls have yet to be built.


The window glass has been installed and the main concourse stands ready for finishing along the Donald Street side of MTS Centre.


This view looks north from main concourse seats. Gravel fill is being removed at the event level, some twenty feet below grade, in preparation for the pouring of the structural slab for the ice floor.


The large construction sign at the Portage and Hargrave intersection announces the MTS Centre opening date of November 15, 2004.